The city scheduled demolition at the Lincoln Court street end to begin Oct. 26. Two of the west side's small public spaces were set to close with it: the Lincoln Court pedestrian bridge over Collins Canal and the green space at the foot of Lincoln Road. The City of Miami Beach gave each closure an expected length. That same month, the contractor building West Avenue Phase II went to court asking to walk away from the job. The weekly closure calendar is precise. The overall finish date is contested.
That is the frame for everything below. The dates in the city's Oct. 15 update are short-range commitments that crews are working to. The completion date for the larger project is a legal question.
What Was Scheduled to Close Oct. 26, and for How Long
The city's Oct. 15 project update lists the closures, their expected start dates and their expected durations.
| Location | Work | Start | Expected closure |
|---|---|---|---|
| Lincoln Court pedestrian bridge | Base of the bridge removed and rebuilt | Oct. 26 | Closed continuously for about six weeks |
| Lincoln Road street-end green space | Retaining wall behind the seawall rebuilt, roadway raised | Oct. 26 | Closed for about one month |
| Lincoln Court street end, north of Lincoln Road | Demolition, then roadway work | Demolition Oct. 26, roadway Nov. 2 | Building access maintained, with coordinated interruptions |
The city says the rebuilt Lincoln Court street end will get new brick pavers, storm drains, sidewalks, a new curb ramp and landing at the foot of the bridge, and rebuilt stairs. If those estimates hold, the green space would reopen around late November and the bridge around the first week of December. That is simple date math from the city's figures, not a reopening date the city has announced.
Parking is the other daily change. The same update lists no-parking zones on Lincoln Road from Alton Road to the street end, on Bay Road north of Lincoln Road, and on 16th Street between Bay Road and Alton Court. Crews generally work Monday through Friday from 7 a.m. to 5 p.m., with Saturdays as needed, and the city says the contractor may work later when needed. The city also asks people to stay out of closed work zones and use the signed detours.
The Rest of the Work Zone Is Mostly Underground
The new street-end closures sit on top of work that was already under way. The Oct. 15 update lists these active zones:
- The pump station at 1671 West Avenue
- Drainage well work on Lincoln Road, between Bay Road and a point east of West Avenue
- Stormwater drainage installation on West Avenue south of Lincoln Road
- Drainage well work on 16th Street, between Bay Road and Alton Court
Most of this happens below the street. What people see at street level is narrowed sidewalks, coned-off lanes and lost curb parking. The west end of Lincoln Road has lived with this setup for a while. In January, NBC 6 reported that the block between Bay Road and West Avenue was closed to cars, with a pedestrian path kept open on the south side. Reaching businesses on the north side could mean walking through the construction zone. In the same report, the city said local and business access remained open. NBC 6 also reported that work on that block began in June 2025.
How the Finish Date Has Shifted Over 2026
Lined up in order, the public record looks like this:
- Original target, June 2026. Ric-Man Construction Florida describes this as the project's original completion date in its lawsuit, as summarized by the Miami Beach Journal.
- August 2026. The Miami Beach Review reported that the Lincoln Road and West Avenue stretch was expected to reach "beneficial occupancy" by the end of summer 2026. Summer has ended, and the city's Oct. 15 update still lists active work there.
- Oct. 12. In a city notice to residents, the City of Miami Beach said Ric-Man had told it the firm might take legal action. The notice said no complaint had been filed yet, that the contract "remains in full force and effect," and that day-to-day work would continue without interruption.
- Oct. 15. The Miami Beach Journal reported that Ric-Man had sued the city. According to the Journal's summary, the contractor says delays caused by the city have pushed completion of the north-of-14th-Street work from June 2026 to as late as 2029. Ric-Man wants a judge to confirm it can terminate the contract and be paid for work already done. The Journal noted the city had not yet responded in court.
The 2029 date is the contractor's claim in a lawsuit. The city has not adopted it as a schedule. On the other side, the city's notice says the contract has its own dispute-resolution procedures and requires the contractor to keep working while disputes are addressed. Both statements can be true at once. Crews keep closing and reopening individual blocks on the city's short-range dates, while the end date for the whole project stays unsettled until the dispute is resolved.
For anyone who lives on these blocks, that makes the short dates the useful ones. Six weeks for a bridge and one month for a green space are specific, checkable commitments. A whole-project completion date is not something any public source can give right now.
What the Finished Streets Are Supposed to Include
According to the city's project page, the project limits are West Avenue from 8th Street to Lincoln Road, including side streets, plus Bay Road from 14th Street to Collins Canal and Lincoln Court from Lincoln Road to Collins Canal. The planned work above ground includes:
- Raised roads and sidewalks, with wider sidewalks
- Buffered bike lanes and a continuous bicycle path along West Avenue
- New street lighting and landscaping
- Upgraded street ends
- A Baywalk segment along the waterfront at 1450 Lincoln Road, for walking and other non-motorized travel, with the upgraded street ends providing access to it
Below ground, the scope includes replacing water and wastewater lines, plus stormwater treatment and pumping. The Baywalk is the piece that ties this fall's closures together. The Lincoln Road street end, the Lincoln Court street end and the bridge landing are all being rebuilt as connections to a waterfront walkway that does not exist yet. When the green space and the bridge reopen, they will be connection points for that walkway.
A Pasta Bar Picked a West Avenue Address for Its First Expansion
North of the project's Lincoln Road limit, A Pasta Bar announced an opening date of Wednesday, Oct. 21, at 1784 West Ave. in Sunset Harbour. That is the former Sushi Garage space, according to Miami New Times. Check the restaurant's own channels for current hours before you walk over.
The family-owned restaurant opened in SoHo in 2017. Its co-founders are Nicola Pedrazzoli, Simone Tiligna and Andrea Pedrazzoli. The Miami Herald reports that Miami Beach is the brand's first expansion, which Pedrazzoli explained by calling the city a "true culinary destination." The Miami Beach room covers 4,700 square feet. A 17-seat chef's counter wraps a freestanding kitchen, and there are 56 seats in the dining room, 28 on the patio and eight at the bar. The room was designed by Alessandro Pasquale, who also designed the SoHo original.
Pasta is made daily in what the restaurant calls a pasta lab and finished in a wok. Specials include pink salmon culurgiones and red-striped fagottini, and a five-course pasta tasting menu is offered for two. The wood-smoked grill is unique to Miami Beach. New York does not have it. Grill dishes include a boneless prime ribeye with café de Paris butter and a cotoletta alla Valdostana with prosciutto and melted Fontina.
Thursday's Walkthrough Is Where to Ask About Dates
Commissioner Alex J. Fernandez is leading an on-site community walkthrough on Thursday, Oct. 29, at 11 a.m. The group meets at Lincoln Road and Alton Road, next to the citizenM hotel, gathers east of West Avenue, and walks west along the south side of Lincoln Road. The city's event listing says the walk is a chance to see the progress firsthand and learn about upcoming plans.
The questions with dated answers fit this walk best. Is the Lincoln Court roadway work still starting Nov. 2? Are the bridge and green space still on track for six weeks and one month? Which block closes next once the Lincoln Court street end is finished? The route runs past the drainage well work on Lincoln Road and ends near the street end where the Baywalk segment is planned. For questions after Thursday, the city lists Public Information Liaison Heather M. Leslie at 305.905.5876 (call or text).
If you own on these blocks and are deciding whether to list during construction or after it, the decision rests on the same uncertainty described above. At Innovatio Realty Group, we build listing timelines around a property's actual surroundings, including construction schedules, access and street-level presentation. Schedule a private Real Estate Strategy Session to work out the right timing for your West Avenue property.